CASE STUDY:
Mega-train LNG Plant

Contractor:

Client:

Location:

Value:

KBR, EPC

Sonatrach Oil and Energy

 

Skikda, Algeria

Circa $2.8 billion

Summary of Works:

The PHC group were delighted to supply management services along with site superintendents for the new “Mega-train” LNG plant at Skikda, Algeria. Our involvement for this project included supply to KBR EPC of Senior Site construction manager, Area site coordinators and twelve site construction superintendents.

Totally “stick-built” two train LNG plant, a unique project involving restricted delivery of prefabricated structural steel and pipework together with all vessels, tanks and heavy equipment. All on-site erection work undertaken by “local” Algerian company, trained, managed and supervised by PHC management and superintendents.